READINESS: Navy Lost 1,891 Days of Attack Sub Operations Waiting for Repairs; Spent $1.5 Billion Supporting Idle Crews.

From 2008 to 2018, most of the planned repairs for the Navy’s fleet of about 50 nuclear attack submarines have started late and run long resulting in a combined 10,363 days of maintenance delays and idle time.

“Our analysis found that the primary driver affecting attack submarines are delays in completing depot maintenance,” read the report. “For example, of the 10,363 total days of lost time since fiscal year 2008, 8,472 (82 percent) were due to depot maintenance delays.”

“Although the Navy has shifted about 8 million man-hours in attack submarine maintenance to private shipyards over the past five years, it has done so sporadically, having decided to do so in some cases only after experiencing lengthy periods of idle time,” read the report. “According to private shipyard officials, the sporadic shifts in workload have resulted in repair workload gaps that have disrupted private shipyard workforce, performance, and capital investment—creating costs that are ultimately borne in part by the Navy.”

What a mess.